Your browser is no longer supported

For the best possible experience using our website we recommend you upgrade to the newest version of your browser.

Your browser appears to have cookies disabled. For the best experience of Construction News, please enable cookies in your browser.

Welcome to the Construction News site. As we have relaunched, you will have to sign in once now and agree for us to use cookies, so you won't need to log in each time you visit our site.
Learn more

CN investigates: AWPR safety allegations cast shadow over £745m bypass

Aberdeen Western Peripheral Route new Blackdog junction

The troubled £745m Aberdeen bypass has been hit by repeated delays and the loss this year of JV partner Carillion. Lurking beneath these problems, CN has now seen damning internal reports and heard allegations of shocking safety standards that have prompted calls for a government investigation.

“It’s a miracle no one has been killed on that job.”

This is the accusation that comes from a source with in-depth knowledge of safety on the £745m Aberdeen bypass, which is now closing in on completion after three tumultuous years.

Plagued by delays, the project is now recovering from the shockwaves of losing JV partner Carillion, leaving Balfour Beatty and Galliford Try to finish the work under the Aberdeen Roads JV.

However, as the scheme strives to meet its latest completion deadline, a fresh controversy is emerging. CN has uncovered statistics that shed new light on the Aberdeen Western Peripheral Route’s safety record and spoken to workers who claim low standards compelled them to quit the project.

“I decided it was either going to damage my professional career or my professional integrity because of the number of accidents and incidents that were happening,” another source alleged to CN.

“I thought there was the possibility that we were going to end up with blood on the floor.”

So how had this flagship project, which required years of detailed planning and political lobbying to get off the ground, become dogged by such serious allegations?

Early problems

Even before there were boots on the ground, the 58 km Aberdeen Western Peripheral Route (AWPR) was hit with delays and cost overruns.

Despite getting the green light in 2009, it took five years and a Supreme Court verdict before a Balfour Beatty, Carillion and Galliford Try joint venture was named as the successful bidder, seeing off a host of rival tier one consortiums in the process.

However, the start of work on site was further delayed by compensation claims from farmers who suffered damage to their land, and pollution concerns over run-off into the River Dee.

The project finally commenced work in February 2015. Now, internal safety reports acquired by CN (which can be viewed here) have laid bare the extent of health and safety incidents during the first year of the project.

These reports show that the average number of accidents per month between February and July 2015 was 5.2. However, this then rocketed to a monthly average of 16.8 between August and December of that year – a rise of 225 per cent.

Of the 115 incidents recorded in the project’s internal documents during its first 11 months, more than half (58) were deemed ‘High Potential’ (HiPo) incidents, meaning they were events which had the potential to result in a fatality.

The most common types of onsite incident on the AWPR during 2015 were service strikes – when machinery hits electrical cables, telephone wires or water pipes ­– which accounted for a third of the total (39) incidents in those first 11 months.

Another frequent occurrence was the overturning of construction vehicles, with 27 such incidents recorded during 2015.

The report shows a number of instances when work was carried out close to oil pipelines owned by Shell and BP without the petrol giants’ knowledge or consent. In one instance, a subcontractor carried out work just 12 m from the pipeline itself.

Traffic collisions are also detailed in the reports, including a crash between a Carillion van and a parked police car, and another between a crane and bulldozer. 

Aberdeen Western Peripheral Route Craibstone Junction Underbridge

Aberdeen Western Peripheral Route Craibstone Junction Underbridge

When CN presented these figures to the project client Transport Scotland, it said it did “not recognise the way in which [the] figures had been interpreted or presented” and declined to offer an alternative interpretation.

CN submitted a freedom of information request for updated data for all years of the project, but Transport Scotland said it could not provide these figures.

Differences in safety data

Prior to CN’s investigation, the only publicly available accident figures for the AWPR were those disclosed by the main contractors’ JV following an FOI request and published in March 2018 by Transport Scotland.

According to the disclosure, there were a total 195 accidents on Aberdeen bypass in the three years from February 2015 to March 2018, with 23 in 2015, 88 in 2016 and 84 in 2017. 

The 23 accidents reported by Transport Scotland for 2015 are 92 fewer than recorded in the internal safety reports obtained by CN.

It appears that Transport Scotland’s FOI publication does not include the High Potential category among its classifications. In the internal safety reports, 58 incidents were recorded under the High Potential classification for 2015.

It is unclear at this stage whether Transport Scotland’s definitions differ in any way from those of the internal reports obtained by CN. Transport Scotland declined a request by CN to explain the definitions in more detail.

When CN presented this data and the interpretation to multiple sources on the project, they questioned the number of near-misses recorded.

They also alleged that Transport Scotland’s FOI response had been selective to avoid the inclusion of a number of serious incidents that occurred over the course of the project. 

This allegation was refuted by Transport Scotland, a spokesperson for whom said: “The context in which this information has been presented is inaccurate and includes assumptions that are not based on fact.”

Speed over safety?

As the AWPR moved through its first year on site and then the second, mounting issues caused by exceptionally bad weather and challenging site conditions began to emerge.

“The priority was on the pace of production. It was the speed of the job was being done that was causing the problems”

Former AWPR worker

Completion dates on the scheme have been pushed back several times, leading to a number of political figures in Scotland weighing in in with criticisms on the lack of progress.

After the Scottish Government revealed a delay to the Balmedie-Tipperty section of the project in late 2016, Conservative MSP Peter Chapman took aim at the JV, suggesting that “the management of the construction must be called into question”. 

The collapse of Carillion earlier this year was followed by further delays to work, as well as £60m-£80m in financial writedowns from the project’s remaining JV partners.

Numerous workers from the AWPR project alleged to CN that progress was put before safety on the project. “The priority was on the pace of production,” one source claimed. “It was the speed of the job was being done that was causing the problems.”

Overstretched and overworked

Another allegation that CN heard repeatedly over the course of the investigation was that safe working conditions were put in jeopardy because supervisors were required to oversee many workers over vast distances.

“It was all about doing as many hours as you could and getting the job done as quickly as you could. We were under intense pressure” 

Former AWPR manager

“I had up to 90 men in the section I was working in,” one project supervisor alleged to CN.  “All the project managers were interested in was go, go, go.”

CN has obtained evidence showing staff on the Aberdeen bypass were repeatedly worked more than 70 hours a week, and some workers managing busy sites for periods of more than 13 hours at a time.

“I was doing 16-18-hour days,” one AWPR manager, who has since left the project, said. “It was all about doing as many hours as you could and getting the job done as quickly as you could. We were under intense pressure.”

The source said they had resigned from the job due to the pressure they were under, having been forced to take three months off work due to stress.

Aberdeen Western Peripheral Route beam installation

Aberdeen Western Peripheral Route beam installation

Scottish Labour leader Richard Leonard has called for the Scottish Government to investigate health and safety on the Aberdeen bypass as a result of the new information.

He said: “This is supposed to be a flagship project for the Scottish Government – and so should be founded on a gold standard of health and safety as well as the terms and conditions of workers on the project.”

When CN put these allegations to Transport Scotland, a spokesperson said that although responsibility for health and safety lay with the contractor, it had been working with it to enhance standards across the site.

A spokesperson said: “Over the past year, the contractor has reported steady improvements through various reporting mechanisms and we will continue to work with them as the construction of this project nears completion.”

Balfour Beatty and Galliford Try were unable to comment directly due to the partnering nature of the project.

As completion of this flagship scheme looms, attention will turn to what might have gone wrong on the AWPR to prompt such serious health and safety allegations – and whether there are lessons to learn for the major infrastructure projects of the future.

You can view the full internal safety documents acquired by CN below

Related files

Readers' comments (1)

  • And let's not forget the wellbeing of the workers! Wellbeing is just as important as health and safety considerations, not to mention that a fatigued workforce is much more likley to make mistakes that lead to an accident.

    Unsuitable or offensive? Report this comment

Have your say

You must sign in to make a comment

Please remember that the submission of any material is governed by our Terms and Conditions and by submitting material you confirm your agreement to these Terms and Conditions. Links may be included in your comments but HTML is not permitted.