Erection of the arch

WEMBLEY

The arch is assembled on the ground

Strand jacks pull on five separate cables connected to the arch truss via the tops of the temporary towers

As the arch passes through the vertical, similar jacks on the backstays help lower it into its final position 22 degrees to the vertical